The right click context menu provides shortcuts to the most used tasks you perform in the Gantt Chart.

To view a description of all of the functions of the left side of the window - Tree List context menu - click here.

Preferences

Hide / Show Toolbar - Toggles the Project window toolbar / ribbon bar

Hide Toolbar / Show Toolbar - Toggles between displaying and hding the Calendar window toolbar.

Hide Text / Show Text - Toggles between showing and hiding the text underneth the icons in the Calendar window toolbar.

Small Icons / Normal Icons - Toggles between showing large or small icons in the Calendar window toolbar

Retore Window Defaults - If you have moved any of the columns or changed the menu set up, Restore Defaults removes all your changes

Set View - Not yet available

Add Task Tasks are the activities for your project. Click here for more information on adding tasks
Edit Task Opens the Task Detail window of the selected task for edititng.
Delete Task Deletes the selected task.
Remove Task from Project Removes the selected task from the project but not from the database. You can then add this task to another project.
Colour Allows you to change the color of the Icon for this group or task
Show / Hide Detail Hiding the detail is the same as clicking on the Normal window icon on the toolbar and hides the detail task window below the treelist and Gantt chart.
Split Mode Split mode is the same as clicking on the Split icon on the toolbar and changes the cursor to Split mode. When in Split mode, click on a task to create a suspension at that point. Click here for more information on adding suspensions.
Edit Project Marker Ribbons

Displays a list of the current project markers, or checkpoint ribbons. These ribbons display a vertical ribbon on the Gantt chart at a given date/time and in a colour of your choosing. From the list you can add, open, duplicate, or delete a ribbon. Click here for more information on Project Marker Ribbons.

Change Date Change date lets you change the date within the Gantt chart. Choices are:
  • Start of Project
  • Today
  • End of Project
  • To Project marker - project markers will be listed in a submenu
  • To Start Date of Currently Selected Task